Did the work change?
Compare the request with the accepted estimate, scope, assumptions and exclusions.
Use this change order checklist to define what changed, calculate the added price and record the schedule impact before paint goes on the wall, supplies get used or labor starts.
A change order is a written record of an agreed change to the original job scope or contract terms. The change may add work, remove work or substitute materials. For a solo painter, cleaner, handyman or small maintenance crew, the practical goal is simple: make sure the customer and contractor see the same added scope, price and timing before the work begins.
Compare the request with the accepted estimate, scope, assumptions and exclusions.
Count added labor, materials, equipment, fees and any movement in the completion date.
Follow the written-change process in the original agreement before starting the extra work.
Use plain language without turning the conversation into an argument.
Original scope: Walls only; closet and damaged baseboard excluded.
Requested change: Paint one closet and replace six feet of baseboard.
Added cost: 3 labor hours × $45 = $135; materials $36; other cost $15. Subtotal $186.
Using a 20% markup: Added price $223.20 before applicable tax.
Schedule: Completion moves by one day. Work begins after the approval required by the original agreement.
Document added windows, appliances or occupied-room cleanup that was not in the accepted cleaning scope.
Document hidden damage found after opening a wall, including new materials, labor and timing.
Document owner-requested substitutions, added areas or access delays that change cost or completion.
Industry references reviewed: Associated General Contractors of America—Change Orders and Procore—How Change Orders Work in Construction.
The original agreement and applicable law control what must be written, signed or approved. This free tool provides general business information and does not replace legal, tax or accounting advice.
The Contractor Quote & Follow-Up Kit includes a working cost-and-margin calculator, scope worksheet, estimate layout, follow-up templates, closeout checklist and project backup.