Before you do extra work, document the change.

Use this change order checklist to define what changed, calculate the added price and record the schedule impact before paint goes on the wall, supplies get used or labor starts.

Free to useNo signupNothing entered is saved

“Can you add one more thing?” needs a clear answer.

A change order is a written record of an agreed change to the original job scope or contract terms. The change may add work, remove work or substitute materials. For a solo painter, cleaner, handyman or small maintenance crew, the practical goal is simple: make sure the customer and contractor see the same added scope, price and timing before the work begins.

Did the work change?

Compare the request with the accepted estimate, scope, assumptions and exclusions.

Will cost or time change?

Count added labor, materials, equipment, fees and any movement in the completion date.

Is approval required?

Follow the written-change process in the original agreement before starting the extra work.

Extra-Work Cost CalculatorChange impact

Include your own working time and any crew time.

$

Use the labor rate appropriate for this estimate.

$

Include consumables, delivery and waste when applicable.

$

Add only costs that belong to the changed work.

%

Markup is applied to the added cost subtotal.

State whether the completion date moves.

Added cost subtotal$186.00
Suggested added price$223.20
Schedule impact+1 day

This calculator runs in your browser. Crown Pro Commerce does not receive or store the numbers you enter. Tax and contract-specific requirements are not calculated.

Before extra work starts

Eight-point change order checklist

0 of 8 checked

A simple way to pause the scope creep

Use plain language without turning the conversation into an argument.

“I can add that. Before I start, I’m going to write down the added work, price and schedule impact so we both approve the same change.”

Example: added painting work

Original scope: Walls only; closet and damaged baseboard excluded.

Requested change: Paint one closet and replace six feet of baseboard.

Added cost: 3 labor hours × $45 = $135; materials $36; other cost $15. Subtotal $186.

Using a 20% markup: Added price $223.20 before applicable tax.

Schedule: Completion moves by one day. Work begins after the approval required by the original agreement.

Cleaner

Document added windows, appliances or occupied-room cleanup that was not in the accepted cleaning scope.

Handyman

Document hidden damage found after opening a wall, including new materials, labor and timing.

Maintenance crew

Document owner-requested substitutions, added areas or access delays that change cost or completion.

Keep one clean record

  1. Number the change so it can be found later.
  2. Reference the original estimate or agreement.
  3. Write the revised scope in specific, measurable terms.
  4. Show the price change and payment timing.
  5. State the effect on milestones or completion.
  6. Attach photos, selections or written requests.
  7. Capture the approval required by the contract.
  8. Store the approved record with the job file.

Industry references reviewed: Associated General Contractors of America—Change Orders and Procore—How Change Orders Work in Construction.

Ready for the complete workflow?

Quote, document, follow up and close out the job.

The Contractor Quote & Follow-Up Kit includes a working cost-and-margin calculator, scope worksheet, estimate layout, follow-up templates, closeout checklist and project backup.